PUBLIC TRANSIT: Nashville unveils schedule for bus rapid transit project

Sept. 28, 2012

The Nashville (Tenn.) Metropolitan Transit Authority (MTA) presented a tentative schedule for its pursuit of funding for the East-West Connector bus rapid transit program on Thursday. Officials hope to have construction completed by the end of 2015 but acknowledged it could extend into 2016.

 

The Nashville (Tenn.) Metropolitan Transit Authority (MTA) presented a tentative schedule for its pursuit of funding for the East-West Connector bus rapid transit program on Thursday. Officials hope to have construction completed by the end of 2015 but acknowledged it could extend into 2016.

The East-West Connector would join Five Points in East Nashville with White Bridge Road in West Nashville, a 7.5-mile route. Total project costs are estimated at $175 million, with a 14-month construction schedule.

MTA will begin work on the federal grant application process in October, with hopes of coordinating with the Federal Transit Administration (FTA) throughout. The agency expects to know more about FTA’s involvement by January.

Under the rest of the tentative timeline, environmental documents would be submitted in April and signed by July. MTA would then begin seeking final design bids for the route itself. At this pace, officials expect the full, formal federal grant application would be submitted in September 2013.

Sponsored Recommendations

Our new Bridge Hanger animation demonstrates how fast and easy it is to install light, sturdy fiberglass conduit onto bridges.
Learn how Champion Flame Shield® Provides a Safe Solution in Fire Sensitive Applications
See how fiberglass conduit stacks up to the competition in crucial areas like weight, corrosion resistance and installation cost.
See how Champion Fiberglass compares to PVC, GRC and PVC-coated steel in installation.