Rich Randall, general manager of ALL Crane Rental of Columbus, credited his sister branches for helping to gather such an impressive line-up of machines for a single project. “In addition to our own yard, we pulled cranes from Cleveland, the ALL Family’s headquarters location, and Jeffers Crane Service in Toledo,” said Randall. “It’s always a team effort, but especially with a project this large. Just the logistics of getting everything delivered on time is a testament to ALL’s logistics team and Ryan Flack here in Columbus.” Randall also praises sales rep Chris Kirk for his work in bringing the project together.
Lewis describes the lift process as requiring precision from everyone involved.
“The 770-ton crane picks the girder closer to the bridge pier, as it is usually the heavier of the pieces, while the 360-ton crane picks the second piece,” said Lewis. “These two cranes then hold their pieces while they are spliced in mid-air and set on the pier cap.” At this point, the work isn’t even half-finished. Once splices are complete, the 110-ton crane holds the set so they won’t fall over (a risk with curved girders) as the two larger cranes repeat their process with two new girder pieces. Once these two new pieces are spliced, the 50-ton crane is used to fly in cross frames. Once the cross frames have joined the curved sections, the girders are stable enough for the cranes to release.
“We’re dealing with boom length in excess of 180 feet,” said Lewis. “This is because the rigging for each piece is 100 feet long – necessary to pick the curved girders at the appropriate center of gravity and then maintain a plumb girder to mate with the adjacent piece.”
This phase of the interchange project, referred to as “Ramp A-2,” involves setting 75 individual girder pieces with lengths ranging from 60 feet to 140 feet and a total weight of nearly 5.5 million pounds. Work is being performed at night, with a goal of completing the splicing and cross-framing of four pieces each work night. Time is precious because the cranes need to be moved to a nearby laydown yard at the end of each night so daytime traffic is not impacted. The necessary crane setup at the start of work and removal at the end take up four hours of each work period.
Work on the interchange ramp will continue through June. Selly and Sands is the general contractor for the project.