The final roadway beat density requirements and now provides a smooth ride along SH 74.
Once the area was open, Caterpillar 637 scrapers and 831 compact rollers worked in the 8-in.-thick subgrade, which contained fly ash. A John Deere 672 with automated machine controls spread the fly ash while a Caterpillar RM 500 added water and handled the mixing. Three Ingersoll Rand SF-125 sheepsfoot rollers operating in vibratory mode compacted the dirt. ODOT demanded a 95% density of the fly ash modified subgrade, and with six passes crews were hitting 98% pretty consistently.
The west service road was the first to be paved. On top of the subgrade, paving crews dropped a 5-in.-thick asphalt base that was made up of an ODOT S-3 PG 64-22 asphalt mix with 1-in. rock. A Caterpillar AP1055E paver with Cat Grade Control and a ski created the mat on the jobsite. A Roadtec Shuttle Buggy also was used. A pair of Caterpillar CB54 XW steel double-drum rollers served as the breakdown, one operating in static mode and the other working in vibratory mode. They were followed by a Bomag BW27 pneumatic roller and a Dynapac CC522 steel double-drum, which served as the intermediate and finish rollers, respectively.
It took a total of 11 passes—seven in breakdown, two in intermediate and two in finish, to reach a density range of 92-97%. A Troxler non-nuclear gauge was used about once an hour to check for density. Haskell Lemon also took cores daily.
The 3-in.-thick intermediate layer contained an S-3 PG 76-28 mix with 1-in. rock, and the 2-in.-thick surface mat called for an S-4 PG 76-28 mix with 5/8-in. chips. The rollers that were used for the base mix were the same for the intermediate and surface lifts, and density also was achieved in 11 passes.
The 2-in.-thick surface mix was used for both the 4-ft-wide inside shoulder and 10-ft-wide outside shoulder.
Supplying the asphalt to the job was a CMI 450-ton asphalt drum mix plant located 12 miles from the project. It produced a maximum of 400 tons per hour. The asphalt was 325°F coming out of the plant and was 300-320°F at laydown. The asphalt content for the S-3 mixes was 4.5% and the air voids were 4.2%. The asphalt content for the S-4 mix was 4.8% and there was a 4.3% air void average. Haskell Lemon used both hot-mix and warm-mix asphalt to create the new SH 74, and the intermediate mix also contained 25% reclaimed asphalt pavement. The recycled material came from the old SH 74 (a Roadtec 900 handled all of the milling operations) and a stockpile at the Haskell Lemon yard.