Crews working during the early stages of the S.R. 36 project, which was recognized by NAPA for quality in construction.
Award-winning asphalt paving
Summers-Taylor was working with a minimum compaction requirement of 92%, and averaged about 7 miles in transporting distance from the asphalt plant. The team used a 7.5-in. sub-base of grade-D base stone, which was mainly limestone, while the base was primarily constructed of clay.
Four different mix layers of asphalt were implemented on the S.R. 36 project, beginning with a 3-in. layer of type 307-AS mix with a maximum aggregate size of 1.75 in. On top of that came a 3-in. layer of 307-A mix with the same maximum aggregate size as the AS mix, followed by a 2-in. layer of type 307-BM2 mix with a 1.25-in. max. aggregate size. Finally, the surface layer was a 1.25-in. 411-D layer with a .5-in. max. aggregate size.
The lab testing at the asphalt plant differed for each mix type. 307-AS and 307-A lab testing requirements were only a gradation check, which was sampled by a belt cut on the virgin aggregate and RAP belts. The 307-BM2 and 411-D required the contractor to test the mix for AC content and gradation using the NCAT oven, along with Marshall pills and rice tests for volumetrics. Those tests were done to determine lab air voids and maximum theoretical gravity.
The 307-A, 307-BM2 and 411-D also required density testing in the field. Even though TDOT checks the density with a nuclear gauge, the contractor tests the density through core samples during the control strip operation. The 307-AS mix did not require field testing.
The paving train on the project was led by a Roadtec 2500 Shuttle Buggy, followed by a Roadtec RP190 paver. An Ingersoll-Rand DD90 vibratory smooth drum roller came after as well as a Hamm HD 90I vibratory oscillating roller in the middle. The finish roller was a Bomag BW11AS static roller.
In total, the team at Summers-Taylor used about 86,000 tons of asphalt and a little over 100,000 tons of stone. The total IRI came in at 44.9. The daily quantities on the binder and BM2 mix were smaller quantities that needed to be done in smaller sections. “But when we came back and did our D mix, our surface mix, we were after probably 2,000 tons a day, which was one complete pull all the way,” Fuller said. “So we did one pull each day on it.”
The National Asphalt Pavement Association (NAPA) awarded Summers-Taylor with a Quality in Construction Award for excellence in construction of an asphalt pavement in 2017.
“In earning this Quality in Construction Award, Summers-Taylor has constructed a safe, quiet, smooth asphalt pavement,” NAPA Chairman Kevin Kelly said in a release.