In 2010, a stretch of I-5 in Skagit County, Washington, was in dire need of rehabilitation. A 1993 asphalt maintenance overlay proved insufficient, suffering severe reflective cracking caused by the joints of the original underlying concrete pavement. The Washington State Department of Transportation (WSDOT) knew it wanted to opt for a long-term solution while also keeping costs low. Officials found the perfect fit for the job: a crack, seat, and overlay process that included an asphalt pavement “deep strength” overlay, resulting in a long-life, perpetual pavement design. WSDOT’s first “Perpetual Pavement by Conversion” project was born.
Taking a crack at it
Restoring an 11.6-mile stretch of northbound I-5 from the Joe Leary Slough to Nulle Road proved successful thanks to perpetual pavement design. It was WSDOT’s first interstate project to use the methodology, which was chosen in part to overcome extensive concrete panel movement (aka “panel rocking”) at the original pavement joints. Prior to construction, this stretch of road was in notoriously rough shape. Jeff Uhlmeyer, P.E., former WSDOT State Pavement Engineer and current Associate Engineer at Quality Engineering Solutions, said the hot-mix asphalt overlay placed on the road in 1993 had gradually eroded over the years.
“Over time, the roughness reappeared, and the road was requiring lots of maintenance to keep the transverse cracks sealed,” he said. “So that's where this job came in. We had to provide a solution.”
When federal funds became available in 2010, WSDOT jumped at the opportunity to move this project forward under an accelerated design, bid, and build process. In just three months, the department prepared and advertised the design-build contract and ultimately selected Granite Construction Inc. as the contractor.
The project would become a truly collaborative effort between WSDOT and Granite when they co-located as a partnering team for the duration of the job. Roadwork began in April 2011 and was completed that October.
A seamless process