By: Bill Wilson
To settle the nerves he just kept making a fist.
After water was added to a mixture that included portland cement, the old asphalt that once formed Main Street (and its sub-base) in the village of Verdigre, Neb.,
Dale Bohac started following the padfoot roller on the job. Every few yards he would bend down and pick up a handful of the new mixture, and if he could ball it up the water/cement ratio was about on target.
“You can do all the math you want in the world, but you need to make it work in the field,” Bohac, a project engineer for JEO Consulting Group Inc., told Roads & Bridges. “So I just reached down and grabbed it, and if I opened up my hand and it all stuck together that meant I was getting enough water into the material.
“As you are going through there, the consistency of the dry material changed. I might have 2 in. of armor coat [tack] or asphalt and then go to nothing. Generally it was within reason but you always wanted to make sure you had water available for the cement to hydrate. “
For years, road funding for the village of Verdigre was dry. City Superintendent Willie Bosanek, who proudly drove around in an old Chevy pickup with personalized license plates that read POTHOLE, usually worked with a $30,000 per year preservation and maintenance budget. After neglecting the roads for nearly 25 years, city officials thought it was time to improve as much as possible and passed a bond. Now the question was what method to use, and after Village Chairperson Dave Wickett placed some calls the answer became obvious. Full-depth reclamation had been performed successfully across the region, and the village of Verdigre called on the team of JEO Consulting (Norfolk, Neb.), GSI (Grand Island, Neb.), Coughlin Co. (Salina, Kan.), and Sta-bilt (Harlan, Iowa) to handle the work that began Sept. 26 and took just seven days to complete.
“They would like to do more [full-depth reclamation], but a lot of these towns are in the same position,” said Bohac. “They only have so much they can afford to put towards the streets out of their general budget. In this area, people are pretty conservative. They are not going to go out and borrow a bunch of money and then figure out how to pay it back later.”
The village of Verdigre was able to cover 17 of its 66 blocks, or just over 25%, at a cost of $347,500. Typical reconstruction of the roadway with hot-mix asphalt would have cost about $650,000, so in the end the village saved just over $300,000, and claimed a 2017 Roads & Bridges/Asphalt Reclaiming and Recycling Association Recycling Award.
“It is the best use of funds they could do to improve these deteriorating streets, because if you asphalt-overlay three or four blocks what do you gain?” said Bohac. “You are really not touching the town, so we were able to take this money and paint a pretty broad footprint and improve the main streets.”