2012 Top 10 Roads - No. 5

Nov. 6, 2012
FOOTPRINT BINDING - Tunnel must ? t into tight quarters

PROJECT: Doyle Drive Battery Tunnel and Temporary Bypass

LOCATION: The Presidio of San Francisco

OWNER: Caltrans

DESIGNERS: Caltrans and Arup/PB Joint Venture

CONTRACTOR: R&L Brosamer Inc.

COST: $57 million

START DATE: April 2010

COMPLETION DATE: June 2012

The Doyle Drive Battery Tunnel has to squeeze into an extremely restricted footprint between the San Francisco National Cemetery and the existing Doyle Drive.

The project is located in the Presidio of San Francisco, a former U.S. Army base. One retaining wall was only 5.5 in. from the cemetery. The project team worked closely with the Department of Veterans Affairs to ensure protection of the cemetery land and historic resources.

The Doyle Drive Battery Tunnel and Temporary Bypass project dug its way into position 4 on the ROADS & BRIDGES Top 10 Roads list for 2012.

The southbound Battery Tunnel and temporary roadway are portions of Phase 1 of the Presidio Parkway. Traf?c was transferred to the new structures in April 2011, and they will carry traf?c until construction of the entire project is complete in 2015. The existing Doyle Drive is an elevated roadway constructed in 1936 and now structurally and seismically de?cient. The new Presidio Parkway will incorporate modern design improvements, wide landscaped medians, continuous shoulders, twin bridges, two sets of short cut-and-cover tunnels and a new interchange providing direct access from

San Francisco.

Excavation of the tunnels was complicated by unrecorded underground utilities. Most of the utilities on the project site were placed by the military in the early 1930s. Since then, records of the network have been poorly maintained, and changes have gone unrecorded. Relocating unexpected utilities delayed tunnel excavation into one of the rainiest winters in recent San Francisco history. A shoring system using struts and tiebacks was designed to support a 30- to 40-ft cut, minimize de?ection and still allow for

removal of nearly 100,000 cu yd of material. To expedite tunnel construction, a custom traveling form system and high-early-strength concrete mix designs were used.

Another challenge was to design the tunnel-systems substation, which needed to be hidden within the structure, because of the lack of available space and the project’s architectural criteria. The substation houses extensive lighting, electrical, telecommunications, traf?c-monitoring and ?re-suppression systems. The design team used 3-D modeling to help visualize and analyze options and determine the most space-ef?cient and constructable solution. With the 3-D modeling, project designers developed a system to reduce bends in rigid conduit and a more ef?cient and accessible substation.

A ?ve-lane temporary bypass road was built at the eastern end of the project to enable traf?c to continue ?owing after the original roadway was demolished and before the ?nal Presidio Parkway is completed.

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...