No. 6 - Highway 63

Oct. 5, 2015

Nobody wants to drive off a cliff, or drive past an unstable one, either. The Highway 63 job went through the downtown area, over the Athabasca River and between the Athabasca River Valley and its shaky cliff. Staged construction, overlapping contracts and almost 2 kilometers of tangent pile, secant pile and 9-meter-high mechanically stabilized earth walls were used to handle the tricky conditions while keeping traffic moving during construction. Crews used launching girders and worked from existing structures to build the river crossings. One of the bridges was built on existing 50-year-old piers.

Location: Fort McMurray, Alberta, Canada

Cost: $450 million

Length: 4.35 miles

Designer: Stantec Consulting Ltd.

Contractors: Flatiron Constructors; Graham Construction; Innovative Civil Constructors; South Rock Construction 

Owner: Alberta Transportation

Sponsored Recommendations

Our new Bridge Hanger animation demonstrates how fast and easy it is to install light, sturdy fiberglass conduit onto bridges.
Learn how Champion Flame Shield® Provides a Safe Solution in Fire Sensitive Applications
See how fiberglass conduit stacks up to the competition in crucial areas like weight, corrosion resistance and installation cost.
See how Champion Fiberglass compares to PVC, GRC and PVC-coated steel in installation.