Harbor Bridge Developer Needs to Fix Flaws in Bridge

Aug. 17, 2022
The developer has 15 days to fix the flaws or be fired from the project

The Texas Department of Transportation (TxDOT) said at a press conference on Tuesday that the developer of the new Harbor Bridge will be fired if they do not fix the design flaws in the bridge in 15 days.

A little over a month ago, TxDOT stopped work on the new Harbor Bridge for fear that the bridge would collapse if work continued on it.

"This is unfortunate, disappointing and unacceptable," Executive Director of TxDOT Marc Williams said about developer Flatiron/Dragados LLC's (FDLCC) "lack of responsiveness" to safety concerns brought by TxDOT.

TxDOT had many questions about the key elements of the bridge.

"Over the course of the project, there have been assurances by Flatiron/Dragados that these issues had been or would be addressed," Williams said.

TxDOT hired a fully independent bridge engineering firm, Systra International Bridge Technologies, to confirm that those concerns were addressed. They found that the concerns were not addressed. 

"Earlier this year, this review identified several areas of concern that generally involved instances where the bridge design did not meet various industry standards specified by TxDOT," Williams said. Issues with foundations, load and weight capacity, and the future stability of mainstay bridge were all included in the review. 

TxDOT sent FDLCC a notice of nonconforming work on April 29, Williams said, to formally let FDLCC know about the concerns after the review was complete.

TxDOT suspended work on the bridge after FDLLC's "lack of responsiveness" to TxDOT's concerns on July 15.

"Despite numerous meetings between TxDOT, the Flatiron/Dragados team, and IBT, Flatiron Dragados has refused to acknowledge the safety issues that have been identified or to take any steps to correct them," Williams said.

"This is unacceptable and places TxDOT in the unfortunate position today of having to provide Flatiron/Dragados with a notice of default."

FDLCC has 15 days to "definitively address the safety issues that have been raised," and if they don't, TxDOT said they will replace them as the contractor. 

"Should we have to move forward with terminating this contractor, TxDOT will expedite the process to move ahead safely and deliberately by securing new contractors to complete the work on the Harbor Bridge, specifically to address the safety issues that have been established and finish the job," Williams said. 

This all may push back the estimated completion date for the new Harbor Bridge, again, Williams said.

"We are going to see this project through to completion," Williams said in the press conference. 

TxDOT held the meeting Tuesday to "reinforce that safety remains our highest priority as we work to assure the new Harbor Bridge is properly and safely constructed," Williams said.

---------------------------------------------

Source: TxDOT

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...