The Pierre-Fort Pierre Bridge Construction is Facing Challenges

March 16, 2023
The new opening date is the summer of 2024

Construction crews are facing challenges with the construction of the Pierre-Fort Pierre Bridge in South Dakota. Originally planned to open in December 2023, the South Dakota Department of Transportation (SDDOT) has to push the opening date back to the summer of 2024.

Dean VanDeWiele, a Pierre-Fort Pierre area engineer for SDDOT, said the delay in the bridges progress is due in part to the complications of working underwater.

“You're just seeing the river water elevation, and so when you're going down you really had to watch the evaluations of your auger as your drilling because you never really know if you got a good bite of clay as you're pulling it up... Or did you not get any clay at all, did you go too deep, and it's very hard for the crane to lift back up?," said VanDeWiele. "So because you couldn’t see, because you're just looking at the top of the river water surface, that was another additional challenge to working below water.”

In 2016, a bridge replacement study was conducted by SDDOT which showed signs of the bridges deterioration which started the project.

The new bridge will serve as the primary crossing point over the Missouri River between Fort Pierre and Pierre.

VanDeWiele said the bridge will have features that increase functionality, user enjoyment, and offer improved aesthetics.

“What's really neat about this bridge is that it will have a 12-foot shared use path. Shared use means that walkers and bicyclists will be able to walk side-by-side, and right now I think we are only at a five-foot width. You feel really constrained walking on the sidewalk across the bridge today, and you feel very close to traffic," said VandeWiele. "It is going to have scenic overlook, they call them belvederes, they are benches out on the bridge, with these bump-outs that you can just sit and look down on the river, look up and down the river. So it's really going to more meet the needs also of today's user, if that makes sense, vs. just cars and trucks.” 

SDDOT said the new bridge is anticipated to be open for traffic usage in the summer of 2024 with an anticipated completion date of the summer of 2025.

----------------------------------------------

Source: South Dakota Public Broadcasting

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...