“As a design-build, we completely changed the basis of design from the RFP drawings, and the overall timeline from design through construction was extremely fast-paced,” Thrall Hershberger, construction manager for Graham Contractors, told R&B. “We were able to prioritize the design of the long-lead item materials, such as the arch itself and the MSE panels, and began fabrication at-risk in order to meet the accelerated schedule. With the full closure, there were schedule limitations due to summer activites in the mountains and the White Pass Ski Resort area, as well as the national forest.”
There was also a month-long delay due to a local forest fire, which precluded use of the planned detour route.
“That happened at the 11th hour,” Hershberger said. “It was within a week of the pending road closure schedule. Equipment, materials, and manpower were already coordinated down to the shift, and they had to be rescheduled.”
Nonetheless, once the threat was quashed, Graham was able to reapply its construction plan in short order.
“We self-performed 85% of the construction work,” Hershberger said, “and that benefited the rescheduling. We subbed out paving and demolition of the original structure and other things, of course.”
When all was said and done, contractors were able to meet the 17-day closure limit—including paving time—before the dense winter mountain weather moved in, and as a result saved WSDOT $4 million in the bargain.
Project: Wildcat Creek Bridge (U.S. 12)
Location: Rimrock, Washington
Owners: Washington DOT
Designer: Stantec/Contech
Contractors: Graham Contractors LTD
Cost: $8 million
Length: 64-ft arch structure
Completion Date: Oct. 22, 2018
About The Author: Budzynski is senior managing editor of Roads & Bridges.