One of the more complex aspects of the bridge’s design for the tied arches was confirming the redundancy of the structural system in the case of damage to the tie beams or loss of hanger cables. “Our design was based on a rigorous dynamic analysis that allowed us to accommodate the sudden loss of even two of those inclined hangers, or any one plate on the tie-girders,” Smith explained. “The design challenge was doing an analysis so that even in the event of a catastrophic loss of major parts of the structure, it would still function.” Tie girder redundancy on the arches was achieved by providing a stitched-up steel box section that can afford the loss of one plate of the section. Longitudinally post-tensioned, precast deck panels composite with the tie girders provided an additional level of redundancy.
Among the most challenging aspects of building the bridge was erecting the complex twin 480-ft network-tied arches over the river. This particular bridge design was chosen to hearken back to the previously existing cantilever through-truss arch bridge. Fortunately for MassDOT, HNTB had extensive experience designing a network tied arch, as the firm has designed eight of the 14 bridges of the same type that exist in the U.S. The new Whittier Bridge brings that total to nine.
The original request for proposal documents envisioned floating the arches to the construction site and hoisting them into place with barge-mounted cranes. “But because of the tidal nature of the river, we determined that was impossible, so we built it with a launch girder.” Aside from the tide fluctuations, the need to maintain a 150-ft navigable channel and working in a constrained space made the barges unworkable. Seeking an alternative, HNTB worked with Genesis Engineering as a consultant for the erection process to develop a unique approach that implemented launch girders and overhead gantry cranes to put the new arches into place. The team used Mi-Jack custom 105-ft rolling gantries to erect both the precast deck and the steel, building the bridge from land on both sides.
Throughout construction, the team wanted to ensure they minimized in-water environmental impacts. This consisted of limiting in-water work to not disturb the migration and mating patterns of the eastern sturgeon, an endangered species in the Merrimack River. One solution to ensure limited impact was for the pier plinths to use granite-faced precast panels doubling as both form liners and cofferdams, which served as an accelerated bridge construction technique.
In the face of extensive challenges, the project team was able to successfully execute the complicated replacement of the Whittier Bridge to completion, providing the new structure with a 75-year design life to accommodate motorists along a widened I-95 for years to come.
Project: Whittier Bridge
Location: Amesbury, Massachusetts
Owners: Massachusetts DOT
Designer: HNTB Corp.
Contractors: Walsh/McCourt joint venture
Cost: $318 million
Length: 1,400 ft
Completion Date: October 31, 2018
About The Author: Bruns is associate editor of Roads & Bridges.