Designing the new approach superstructures included four separate segmental concrete box girder bridges with a total length of more than 10,600 linear ft. The span lengths for the two side-by-side structures vary from 125 ft to 272 ft. The box girders were built using a self-launching, overhead gantry truss, while the approach bridges were built with segmental cantilever construction to eliminate the need for falsework and to allow the bridges to be constructed over traffic and existing structures. The approach bridges include a 36-ft-wide roadway that increases to 48-ft-wide at the abutments to accommodate acceleration and deceleration lanes. The southbound structure is designed to accommodate future light rail on the west overhang. The northbound structure includes a 12-ft-wide shared-use path on the east overhang. The two structures also carry a fire standpipe, drainage, and 38 other miscellaneous utilities enclosed within the boxes.
The roadway was widened to four 12-ft lanes with a concrete median barrier and 5-ft shoulders compared to the original roadway of 10-ft lanes with no median barrier or shoulders.
The design team developed a concept that permitted new floor system construction above the existing floor, allowing one lane of traffic in each direction to flow during peak hours. With additional weight on the structure and increased wind loads, the team added more than 4,000 tons of steel plates to strengthen the arch. The strengthening design methodology, certified by Purdue University’s Bowen Laboratory, brought the bridge into compliance with AASHTO LRFD requirements. More than 100,000 rivets were replaced with high-strength bolts as part of the strengthening process.
Bayonne Bridge Project Provides 1500 Jobs Annually Through Construction
The project provided nearly 1,500 jobs annually throughout construction—an estimated $380 million in wages and $1.6 billion in economic impact for the region. The previous roadway discharged untreated stormwater directly into the Kill Van Kull waterway. Drainage improvements eliminated these discharges by collecting and routing water for treatment—removing 80% of suspended solids and 40% of pollutants. The waterway and bridge are also possible breeding locations for more than 70 bird species, including the state-listed endangered Peregrine Falcon. As such, the team, with New York State Department of Environmental Conservation, New York City Department of Environmental Protection, and New Jersey Department of Environmental Protection wildlife biologists, made significant efforts to protect fowl habitats. Removing half the approach span piers improved air, light, and viewing conditions, and allowed parks and waterfront access.
The project also included fully automated tolling, a fire suppression system, new mechanical and electrical buildings on each shoreline, aesthetic lighting, security enhancements, and a bridge health monitoring system.
When asked about how this six-year endeavor finally closed out, HDR/WSP Lead Engineer Joseph LoBuono, P.E., told Roads & Bridges: “This has been the project of a lifetime. I have been involved from the initial feasibility phase through to the completion of construction. Strong partnership of Port Authority staff and the consultant designers made this project happen. It has been an honor to work on a project designed by the legendary engineer Othmar Ammann and to perform our work to extend the life of his work for another 100 years—while bringing it up to current codes.”
Bayonne Bridge Project Details:
Project: Bayonne Bridge
Location: Staten Island, New York & Bayonne, New Jersey
Owners: Port Authority of New York & New Jersey
Designers: HDR and WSP
Contractors: Skanska-Koch/Kiewit
Cost: $1.08 billion ($180 million for arch)
Length: 7,160 ft (structure); 10,991 ft total
Completion Date: February 11, 2019
About The Author: Budzynski is senior managing editor of Roads & Bridges.