Reuse instead of replace
By late 2015, the Kansas Turnpike Authority (KTA) faced a dilemma: Much of its aging infrastructure was coming to the end of its useful life. KTA developed a 10-year program to preserve, modernize, and enhance the system. But with so much work needed and a desire by KTA to cash flow projects, a way was needed to stretch resources.
Among the projects slated for funding was the need to raise bridges on I-35 and I-335, along a 180-mile stretch between Topeka and the Oklahoma state line. KTA needed to raise the vertical clearance of many of its bridges along this corridor by 12 to 21 in. to accommodate oversized loads, which are increasingly common on today’s highways. These trucks were being regularly rerouted around KTA facilities because they could not fit under the bridges. It was both a safety problem and a nuisance to freight traffic, and it resulted in significant lost revenue for the turnpike authority.
After analyzing the problem, Burns & McDonnell had an idea. Instead of conventional bridge repair methods that could include replacements, the firm suggested using a system of hydraulic jacks to simply raise the bridges, leaving the original concrete and steel structures intact. The savings would run into many millions of dollars, all while the work could be completed under live traffic, thus limiting the impact to turnpike users.
After modeling and testing the proposed solution, the team finalized a plan to utilize a system of hydraulic jacks to slowly and carefully lift the bridges off their original concrete piers. With many of the bridges weighing as much as 300 tons, it needed to be a meticulous and carefully planned process.
The project involved raising bridges—some were as low as 14 ft—to a minimum height of 15 ft, 9 in. For each bridge, the construction team used up to 20 hydraulic jacks to carefully push up to 600,000 lb of steel girders and concrete deck upward, 1 in. at a time. Within eight hours of jacking, shimming, inspecting, and repeating, the bridges rested on new bearings, secured with steel anchor bolts.
Then, bridge approaches at both ends were regraded, with new guardrails installed and new road signs posted. The project concept has avoided the need for new rights-of-way, easements, or utility relocations.