Crews conducted tests on the newly installed west approach of the bridge.
The takeaway
The west approach slab of the Bayou Courtableau Bridge, with the new design method, kept its contacts and supports from the embankment soil during the first static load test at the time the bridge was ready for traffic. However, during the second static load test 18 months later, the west approach slab had lost most of its supports from the embankment soil, but with less observed faulting at the R/S joint and with better rideability. The maximum measured contact pressure underneath the west approach slab decreased from 10.3 kPa (during first static test) to 3.4 kPa (during second static test), while at the same time the pressure increased underneath the footing mainly due to load transfer caused by increased slab rigidity. On the other hand, the east approach slab, with the traditional design method, showed slightly gradual loss of its contacts from the embankment soil starting from the bridge abutment side towards the pavement side. The maximum measured contact pressure underneath the east approach slab increased from 7.6 kPa (during first static test) to 9.7 kPa (during second static test).
The maximum measured strains in the geogrid due to the 20-ton truck loading were considerably lower than the 2% strain (max strain at 0.3 m below footing < 1%), which is the typical design strain value published by geosynthetic manufacturers.
The roughness profiles demonstrated better performance in the new approach slab system (west approach slab) compared to the traditional design method (east approach slab) with much lower IRI values. The maximum IRI 7.6 m of west approach slab remained almost constant (about 4.7 m/km)
from March 24, 2011, to Jan. 15, 2014, while the maximum IRI 7.6 m of the east approach slab increased significantly during this period (from 8.4 m/km and 5.7 m/km to 11 m/km and 8.5 m/km for westbound and eastbound).
The improved performance of the new (west) approach slab system as visually observed in the Bayou Courtableau Bridge demonstration project after a monitoring period of a year and half indicated to researchers that the application of the new approach design would have desired application to further distressed bridge approaches.
About The Author: Chen is a research associate at Louisiana State University. Farsakh is a research professor at Louisiana State University.