By: Bill Wilson
When the flames were still full of life, the Georgia Department of Transportation (GDOT) was staring at plans from about three decades ago.
The I-85 bridge over Piedmont Road in metro Atlanta was burning on March 30, but officials were hopeful portions would be spared, and they wanted to be ready. So before damage could be assessed, before emergency responders even had the upper hand on the fire that was engulfing the bridge, GDOT had the original designs out and started considering what might be needed in way of repair.
“We knew, as did the public, that one span had to be replaced,” Marc Mastronardi, GDOT construction division director, told Roads & Bridges.
According to Mastronardi, the existing bridge had AASHTO type 5 prestressed concrete girders in place, which are no longer common. However, GDOT designers were confident a special prestressed concrete girder could be designed and allowed for retrofitting with today’s specifications.
When the smoke cleared, six spans—three northbound and three southbound (100-ft section)—were lost due to the heat damage, and the salvageable substructure was limited to portions of the columns. C.W. Matthews Contracting Co. Inc., which in 2001 repaired I-285 over S.R. 400 following a tanker fire, was selected as the prime contractor for the rebuild.
Speeding in place
When GDOT was going over options to replace the damaged portion of I-85, accelerated bridge construction, where a deck is slid into place, was immediately crossed off the list. The bridge, and I-85 itself, is not surrounded by available landscape. Over 240,000 vehicles travel the route every day, so a quick rebuild was essential. The agency also was approached by many companies that make temporary bridge structures, but the elevation of the roadway and skewed angle of the bents made that an impossibility. Since all of the columns survived the blaze it was decided to execute accelerated construction in-place so the bridge could reopen by June 15.
After DH Griffin rubblized the decks and beams that needed to be removed over the course of seven days—which resulted in 13 million lb of debris—columns were cut beneath the cap and jacketed with additional steel and concrete. Four caps also were poured in-place to make way for beam placement and typical construction. Twenty-eight No. 9 and 10 bars, depending on the column, were added vertically to the remaining core with hoops rising on 12-in. centers to the bottom of the cap. Crews utilized a 24-hour concrete mix design that included fiber in the pours. Design strength of 3,500 psi was achieved in 19 hours, on average.
At press time, 31 of the necessary 61 beams were already in place, and all of the beams were supposed to be set by April 26.
Of the six spans two are trapezoidal and two are curved, so the beams will have slight differences from interior to exterior in both directions.
“The trapezoidal sections are all single-cast design and it only takes one beam to hold the whole job up,” said Mastronardi. “Every couple of days it looks like tremendous progress, but the bridge deck work is a little more tedious. That is when the job will slow down a little, as far as perception goes.”