Interstate Bridge Replacement Project Announces New $6 Billion Estimate

Dec. 12, 2022
The new estimate reflects the current conditions, risks, and opportunities

The Interstate Bridge Replacement Project (IBR) that plans to provide a connection between Washington State and Oregon is estimated to be $6 billion according to Greg Johnson, Interstate Bridge Replacement program administrator.

According to a press release, the new projected cost identified an estimate range of $5 to $7.5 billion, which was created by internal and independent experts, including a rigorous process that considers cost escalation and inflation factors affecting transportation projects across the country. Those factors include historically high inflation rates, workforce shortages, materials cost increases due to supply chain issues, and other market conditions.  

“Construction projects across the country are experiencing unprecedented cost increases due to supply chain issues and increasing material and labor costs as well as other factors, and our program is no exception,” said Johnson. “We are confident that the program will land within the projected cost estimate range, and we are actively working to secure funding and manage cost escalation risks.

Previously, the cost estimate was in the high end of $4.8 billion when it was developed in 2020, based on the scope of the previous Columbia River Crossing project. The new cost estimate for the IBR program covers the components of the Modified Locally Preferred Alternative, which in July 2022 was discussed with the Bi-State Legislative Committee and endorsed by the regional program partners of the Executive Steering Group.  

The new estimate sets the foundation for developing the program’s financial plan, anticipated in early 2023, which will include additional details on estimated funding sources and financing approach. Funding for the cost estimate will require revenue from a diverse range of sources, including federal funds, state funds from both Oregon and Washington and tolling. The anticipated cost falls within the range of confirmed and potential funding sources currently identified, which include:  

  • Existing state funding - $100 million 
  • Connecting Washington transportation package - Mill Plain Interchange - $98 million 
  • Move Ahead Washington transportation package - $1 billion 
  • Anticipated Oregon funding - $1 billion 
  • Toll funding – $1.25 - $1.6 billion 
  • Federal grants - $860 million - $1.60 billion 
  • Federal Transit Administration New Starts Capital Investment Grants - $900 million - $1.1 billion 

“Controlling costs for a mega project like the Interstate Bridge Replacement program is a dynamic process, and we will continue to identify and refine possible funding sources and address cost escalation risks and opportunities,” said Johnson. “As we work to minimize costs within our control, we will keep our focus on delivering a multimodal replacement bridge and transportation corridor that keeps our region’s economy moving and improves safety. Regional and national partner support, combined with state and federal funding which we have already received and for which we are well positioned, presents us with a unique window of opportunity to get this project completed.” 

---------------------------------------------------

Source: Interstate Bridge Replacement Program

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...