Massive PennDOT Project a Year Ahead of Schedule

Aug. 1, 2024
Construction on U.S. Route 1 to be split into three phases

As it finishes Phase 1 on its U.S. Route 1 project, the Pennsylvania Department of Transportation (PennDOT) is already a year ahead of schedule. The $111 million project will be split into three phases, and it will widen and upgrade the highway in Bucks County. 

Crews will be expanding U.S. Route 1 to three lanes in each direction and improving the pavement and drainage. The final paving will begin next spring. 

Two new bridges are almost complete as the project heads towards Phase 2. Crews are working on the new northbound bridge at Neshaminy Creek, working on the abutments and center piers. The southbound bridge is completed. 

Deck construction on the U.S. Route 1 southbound structure over the Penndel/Business 1 Interchange finished in late spring, according to PennDOT.

Construction continues this summer, focusing on the bridge’s approach pavement, completion of parapets and installation of sound walls. PennDOT says the southbound bridge is expected to be completed by late summer. 

The southbound U.S. 1 bridge over Rockhill Drive is almost complete. Deck beams were set in April and deck construction is expected to finish in the fall. Parapet construction will be completed later this summer. 

Phase 2 of the project aims to improve four miles of U.S. Route 1. Several bridges will be built and interchanges will be improved. 

The current phase is expected to finish a year ahead of schedule, by mid-2025.

-------------------------------------------------------

Source: Patch, Bucks Co. Today

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...