Contract Termination

Aug. 29, 2024
An unpredictable case teaches hard lessons to each party involved

Court decisions are “opinions.” There are majority and dissenting (disagreeing) opinions. Consistency in opinions across different courts, judges and cases promotes certainty and efficiency. Although courts may strive for consistency as they apply the facts of each case to the applicable laws, opinions can be varied and unpredictable. Opinions differed in this case involving more than six different judges. 

In May 2016, the Federal Highway Administration (FHWA) contracted for improvements along Grand Loop Road in Yellowstone National Park, plus nearby parking areas, trails and scenic overlooks. The work was to be performed over the course of three construction seasons, with planned shutdowns during the winter and certain bird migration seasons. Final completion was planned for October 2018.

In late May 2016, FHWA issued notice to proceed. Within 20 days, the contractor was to submit an “initial schedule” for completion, which was to account for the planned shutdown periods and timely completion of all the work. While performing onsite work in August 2016, the contractor submitted three proposed schedules. FHWA denied all three schedule proposals for lack of compliance with the shutdown periods and other project requirements.

In October 2016 and again during the 2016-2017 winter shutdown, the contractor again submitted proposed schedules, this time with written analyses addressing FHWA’s prior rejections. FHWA did not respond. Subsequently, FHWA requested, and the contractor submitted, another proposed schedule. The contract also provided a detailed presentation to explain how the project would be timely performed within the required parameters.

On Feb. 1, 2017, about one week after the most recent submission and presentation, FHWA terminated the contractor for default. At the time, FHWA explained the default termination was due to the contractor’s failure to diligently prosecute the work.

On appeal to the Federal Civilian Board of Contract Appeals, the Board stated that the propriety of FHWA’s termination decision depends on whether the FHWA “carefully examined the contractor’s ability to complete the work before the contract completion date.” The Board made extensive factual findings after a formal hearing and found the FHWA did not properly consider the narrative explanation accompanying the contractor’s critical path schedule submission.

The Board converted the default termination to a termination for convenience under the contractual conversion clause. The difference for the contractor was the expungement of a default termination from its record, which may affect future bonding, and the contractor’s ability to recover payment for work actually performed, including profit. 

FHWA appealed the Board’s decision to the Federal Circuit Court of Appeals. The Federal Circuit Court stated the propriety of FHWA’s termination decision depends not on whether the FHWA’s examination was careful, but whether the termination decision was reasonable in light of all the facts and circumstances that existed when the decision was made. In other words, the proper point of view was not that of the FHWA, as the Board had applied, but the point of view of a hypothetical third-party under the same facts.

The reviewing authority (the Board in this case) owes no deference to the prior decision. The review begins with a clean slate and depends upon extensive factual findings developed before the reviewing authority. (The decision of the Court was made by two members of a three-judge panel. The dissenting judge criticized the other two judges for not reviewing the extensive factual findings developed by the Board.) Department of Transportation v. Eagle Peak Rock & Paving, Inc., 69 F.4th 1367 (Fed. Cir. 2023). 

The takeaway for contractors is to timely provide complete submittals with explanations. Here, the contractor provided what was a good explanation, but untimely.

The takeaway for owner/decision-makers is to carefully document and rationalize decisions so that, when someone else later reviews the decisions, they can more efficiently agree. 

The takeaway for the legal community is that predicting outcomes with certainty is difficult, if not impossible. RB

About the Author

Jon Straw

Jon Straw is a partner with Kraftson Caudle, PLC, a law firm in McLean, Va., specializing in heavy-highway and transportation construction. Straw can be contacted via e-mail at [email protected].

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...