By: Steve Kuntz, P.E., DBIA
As the only interstate highway running east-west between Washington, D.C., and northern Virginia, I-66 is a heavily traveled commuter thoroughfare.
The Virginia Department of Transportation (VDOT) has overseen ambitious improvements to relieve congestion through the years, including a recently completed, four-phase improvement program to increase capacity and improve traffic flow on I-66 and Rte. 29 in western Prince William County. The phased improvements culminated with the completion of the I-66/Rte. 29/Linton Hall interchange and railroad grade separation project, which was designed by Dewberry under a design-bid-build contract to VDOT.
The $76 million interchange, which opened in 2015, has resolved numerous congestion and safety issues, including the elimination of a signalized intersection at Rte. 29 and Linton Hall Road and two at-grade crossings with Norfolk Southern Railway that had been the scene of several train-vehicle collisions. The centerpiece of the project is a single-point urban interchange (SPUI) and a braided-ramp complex along southbound Rte. 29 that grade-separated Linton Hall Road and Rte. 55 (John Marshall Highway) over Rte. 29. The interchange provides dual or triple left-turn lanes at Linton Hall Road and Rte. 55 to and from Rte. 29. Route 29 also was widened to six lanes and, with the elimination of driveway entrances and two traffic signals, converted to a limited access highway for approximately 1 mile from Virginia Oaks Drive to I-66, enabling the efficient flow of traffic to and from I-66 and points south.
The project created direct ramp access to and from adjacent I-66 via the braided ramp network along Rte. 29 to Linton Hall Road and Rte. 55, eliminating short weave areas and supporting high levels of traffic mobility. The design accommodates ongoing economic development, with several large retaining walls incorporated to avoid impacts to an adjacent retail development.
Walling it in
Prior to construction or relocation of utilities, right-of-way and easements were acquired from more than 60 properties, including complete acquisition and relocation of businesses on 15 properties. Phased acquisition of right-of-way allowed utility relocations as well as construction of detour roads and new access roads to be initiated before all right-of-way acquisitions had been completed, ultimately accelerating the project schedule by more than one year. Construction was separated into three contracts covering building demolitions; utility relocations, detour road construction and access road construction; and finally construction of the interchange. The final interchange phase of construction included four bridges, 10 MSE retaining walls consisting of 288,000 sq ft of precast concrete panels, approximately 950,000 cu yd of embankment, concrete crash walls along the railroad, 10 interchange ramps, three new local access roadways, three traffic signals, overhead signs, ground improvements, roadway lighting, stormwater management facilities, and numerous utility relocations. Additionally, new pedestrian and bicycle accommodations, which had not previously existed, now provide safe multimodal alternatives along Rte. 29, Linton Hall Road and Rte. 55.
Architectural treatments and aesthetic elements also were important to the project. The retaining walls have avoided or minimized impact to the adjacent town center and nearby developments. Architectural treatments were incorporated on each of the walls and bridge abutments. The paint on traffic signals, light poles and light fixtures matches the color and finish of adjacent development features. Landscaping, including ground covers and street trees, has enhanced the streetscape along Linton Hall Road and the elevated ramps approaching the SPUI.