Report claims I-4 Ultimate project in Orlando nearly nine months behind schedule

May 9, 2019

While work is nearly 60% finished, the project builder estimates the timeline for completion could by delayed by 260 days

The I-4 Ultimate Improvement Project in Orlando, Florida, is reportedly falling behind on its scheduled 2021 completion date by nearly nine months.

According to local reports, I-4 Mobility Partners, the project builder, recently told the Florida DOT (FDOT) in a progress report that the $2.3 billion road construction project is delayed by around 260 days. The builder said the new project completion date could now be Sept. 23, 2021

FDOT has said that details in the progress report are being reviewed and are subject to discussion, and that no time extensions or financial considerations have yet been granted.

The project is almost 60% complete, according to the latest progress report. Some of the factors playing into the delay of the construction timeline include affects from Hurricane Irma, foundation design flaws, a cracked bridge pier, delayed opening of a bridge, and two added tolling sites. Additionally, alleged opposition from local governments to requests for lane closures and detours have contributed to the schedule setbacks. 

The I-4 Ultimate had run into other trouble earlier this year, as the project had been shut down for a week after a 59-year-old worker was hit in the head and killed by a 20-ft-long iron pipe on Feb. 4. This was the fourth worker killed since the 21-mile project began in 2015. Just a few days after the project reopened, three more workers sustained minor injuries after falling 15 ft from an elevated platform. 

The I-4 Ultimate project is a P3 effort involving reconstruction and expansion of a 21-mile stretch of I-4 moving into the heart of Orlando. Work on the project began in 2015, and the project limits run between Orange County and Seminole County. Work includes added toll lanes along a 21-mile section from north of State Road 434 in Seminole, through Orlando, and to west of Florida’s Turnpike in Orange County.

-----------

Source: Orlando Business Journal / Orlando Sentinel / ClickOrlando

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...