Single heavy-highway projects exceeding $25 million are not common for New Mexico, and the contractor faced a number of major challenges—including managing traffic and the installation of temporary shoring. The priority to reduce impacts to traffic meant performing a majority of paving operations overnight for AUI Inc. “People were continuously using the intersection, so we did a lot of closures at night to keep the public moving,” Garcia explained. “We had hired a PR person to make sure they were in contact with the public at all times. We did radio advertisements, we had a website—everything going to make sure everyone was informed. I don’t think we impacted traffic that much because we hardly got any bad responses while we were working out there. We had two lanes of traffic flow at all times.”
The temporary shoring was used to construct a new retaining wall as well as a new box structure to serve as the new northbound off-ramp, and the shoring was adjacent to live traffic in a limited work area. In order to build the northbound off-ramp—which is a box structure that goes underneath the interstate—the team had to drive sheet piling there and subsequently place southbound traffic onto the northbound side of traffic. “So we had to create a detour to widen out northbound so we could accommodate four lanes—two lanes coming in, two lanes going out—to construct that area,” Garcia said. “And then we had to drive sheet piles on that too. And we drove 50- to 65-ft sheet piles to retain the earth to keep northbound traffic flowing. And once we did that, we were able to construct the northbound off-ramp section—the tunnel section—which was a big box culvert. But we had to excavate down to 40 ft to make that work. Once we built that side, we threw everybody on the southbound side and built the northbound lanes.”
During the course of the project, nearly 1 million cu yd of dirt were excavated in total. The excavation process proved to be a challenge due to project phasing, as phases of the project were running concurrently while not always using or removing dirt at the same rates. AUI proposed a solution to this issue by stockpiling material currently on the site and using it where it was needed at a later time as opposed to removing it and needing to excavate additional material.
The creation of the retaining wall structures proved to be an obstacle itself on the project, as the unique ribboned artwork design selected for the walls was time-consuming for the contractor to complete. “The challenge of building it was getting the pattern done correctly because we cut all the form ourselves to fit what was on the design,” Garcia explained. The custom forms were created and engineered in the field to create the look and finish required for the design. “All the field measurements were given out to our guys, who were able to lay everything out without a hitch. So just installing the formline and lining it and all that stuff was pretty time-consuming.”
The completion of this project marks the largest that AUI Inc. has ever constructed, which is all the more impressive that the contractor finished up work a week in advance of expected completion. The reconstructed I-25/Rio Bravo Boulevard Interchange was opened to traffic in the first week of July 2019.
Project: I-25 / Rio Bravo Boulevard Interchange
Location: Albuquerque, New Mexico
Owners: New Mexico DOT
Designer: AECOM
Contractors: AUI Inc.
Cost: $55 million
Length: 2.5 miles
Completion Date: July 2019
About The Author: Bruns is associate editor of Roads & Bridges.