NO. 8 ROAD: Reshaping a Growing Community

Dec. 3, 2022
The East Kellogg Expansion and Improvement project is helping an area expand its changing traffic needs

Studies on economic growth showed an increase in population and housing in Wichita which would impact East Kellogg, exceeding the expressway capacity. This led to the redesign of the freeway and the East Kellogg Expansion and Improvement project. This project was a vital route through Wichita, along the US-54/400 highway.

Originally planned as two separate projects – the first being the Webb Road Interchange and the second the Greenwich Road Interchange – the bid for the second project came insignificantly over the engineers’ estimate, so the team thought they could reduce the cost by redesigning the interchange with US-54/400 and the Kansas Turnpike Authority connections. It was also crucial to expedite the design of the Greenwich Interchange Project so both projects could be constructed concurrently. This saved the project approximately $50 million while also accelerating the construction by five years.

TranSystems led the design team, completing the design in 12 months. The design took Kellogg from a signalized expressway to a full freeway section with continuous frontage roads and several interchanges and U-turns. Along with managing the project, TranSystems was responsible for the concept development, freeway, ramp, frontage road, signing and traffic control designs, and some individual bridge designs.

WSP led the design of the revised Webb Road Project and had TranSystems as a major subconsultant. The design of the revised Webb Project included the design of the freeway expansion of East Kellogg and the design of the roadways, retaining walls, a bridge at Webb Road, a drainage system, utility relocation/coordination, and project management. TranSystems was responsible for the concept development, traffic control, and frontage road designs.

There were several challenges throughout the design and construction of the project. In the early stages, the road drainage system was believed to require a storm water pump station at Webb Road, however, it was determined that this section of the project could be gravity drained without a pump station. The elevated sections of Kellogg eliminated the need for a storm water pump, which saved construction and long-term maintenance approximately $2 million.

“While there were many challenges faced throughout the East Kellogg project, collaboration played a key part in getting the project off the ground and seeing it through to completion,” said Brett Letkowski, Principal and Senior Vice President at TranSystems.

Bi-monthly construction meeting were held as the project moved into the construction phase. The team coordinated everything that was happening and reviewed an ongoing 45-day projection provided by the contractor.

The contractor requested a redesign of the soldier pile wall system at one point. Luckily, the project team was able to reduce the number of tiebacks, which lead to less soldier pile walls being needed. In doing this, the team not only saved time, but $1 million.

Another change the contractor proposed was the phasing of the project to pave all the mainline at one time, instead of between two projects. The team got it done, and in the end saved time on the project, as well as made the construction smoother. 

The project was delivered five years earlier on September 23, 2021 thanks to accelerating the Greenwich construction to coincide with the Webb Road Interchange. In doing so, the team not only finished the project early, but also saved approximately $50 million. R&B

Project: East Kellogg Expansion and Improvements

Location: Wichita, Kansas

Owners: Kansas Turnpike Authority

Designer: TranSystems Corporation, WSP

Contractor: Wildcat Construction

Cost: $171.5 million

Length: 2.4 miles

Completion Date: September 23, 2021

Sponsored Recommendations

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...

Transform Your Concrete Highways: The Game-Changer for Long-Lasting PCCP Joint Protection

Concrete highways are a critical piece of infrastructure in the United States, essential for the reliable transportation of people and products. Yet in many cases, their service...