Aging Bridge restored with GeoTree RenewWrap

July 5, 2022

Background

In 2018, an inspection of a Broward County-owned bridge on Flamingo Rd. in Miramar identified structural issues. The Florida Department of Transportation bridge inspection report identified issues including concrete spalling and cracks. The structure, which was constructed in 1956 and experiences approximately 1,800 crossings a day showed signs of deterioration and Broward County expedited design improvements to the bridge well in advance of conditions becoming unsafe. The task of making the bridge repair was part of the County’s Mobility Advancement Program and was managed through the Highway and Bridge Maintenance Division (HBMD).

Solution

HMBD used an innovative design and construction method which minimized the construction impacts to the public by mainly working on the underside of the bridge. This methodology included the use of fiber reinforced polymers (FRP) to strengthen the bottom side of the bridge slab. The project was put out for proposal and FG Construction of Tamarac, FL was selected by the general contractors for the project. With a long presence in the area and experience with FRP repairs, FG was a strong choice to execute the repairs. Originally FG reached out to their normal supplier of construction materials, but in the midst of a global supply chain crunch, the long lead times for product created an issue with completion of the project in the desired timeframe. Fortunately, GeoTree, a company focused on providing solutions for the repair of critical civil infrastructure, had foreseen the supply bottleneck and was able to answer the call by providing the FRP materials within days.

GeoTree’s RenewWrap CF600 fabric was chosen to complete the challenging project which saw the fabric applied perpendicular to the direction of the bridge to provide flexural slab strengthening to the structure. Installation was to the underside of the active bridge, so it had to be completed from a fixed platform from below with the installation team working overhead.

RenewWrap CF600 fabric applied perpendicular to the direction of the bridge to provide flexural slab strengthening.

The fabric was hand saturated and applied using the wet lay-up technique. To reduce the need to regularly mix resin, RenewWrap LPL (long pot life) epoxy was utilized. This led to a more efficient application process which meant the six-person installation team took just a week to complete the project. In all, 3600 square feet of material was used to complete the project.

GeoTree trainer Todd Lyda was on-site throughout the application to supply on-the-go support and to answer questions as needed.

GeoTree Solutions President John Hepfinger said: “We’re delighted that this project has enabled us to build a strong working relationship with FG Construction and that the company is now familiar with our range of products and solutions.        

Sponsored Recommendations

The Science Behind Sustainable Concrete Sealing Solutions

Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...

Proven Concrete Protection That’s Safe & Sustainable

Real-life DOT field tests and university researchers have found that PoreShieldTM lasts for 10+ years and extends the life of concrete.

Revolutionizing Concrete Protection - A Sustainable Solution for Lasting Durability

The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...

The Future of Concrete Preservation

PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...