TRANSIT: Oklahoma City streetcar project takes shape
March 20, 2017
The 5-mile-long stretch of a downtown Oklahoma City streetcar line is set to start operation at the end of 2018
Crews are installing rail and pouring concrete this week on Joe Carter Avenue in the Bricktown area of Oklahoma City for the MAPS 3 streetcar. Herzog Contracting Corp., in a joint venture with Stacy and Witbeck, has a $50 million contract to build the streetcar line.
Altogether, 4.9 miles of track will be laid between Bricktown and Midtown, through the central business district. Rails were welded into 354-ft sections in preparation for installation.
Once rails were installed, workers spread concrete in the newly constructed track bed. While rail was being installed on Joe Carter, pavement was being dug up on E Reno Avenue as work progressed.
Track installation is expected to be complete in about 18 months. The first of seven streetcars is expected to arrive from Pennsylvania this summer, and service is to begin in December 2018.
Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...
The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...
PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...