By: Tim Bruns
Travelers along I-64 between Newport News and Williamsburg may be headed for several attractions in the coastal region of Virginia.
This includes Colonial Williamsburg, the largest living history museum in the U.S., as well as two of the largest theme parks on the East Coast—Busch Gardens and Water Country USA.
These attractions, in addition to a particularly large concentration of military bases in the area, have created the conditions for a rather congested I-64, which previously only carried four lanes of traffic. The Virginia DOT (VDOT) saw fit to widen the interstate to a total of six lanes, adding a 12-ft lane in each direction and a 12-ft shoulder. This work is part of the department’s overall effort to improve mobility on the Virginia Peninsula through the I-64 Widening Project.
The second segment of the I-64 widening is located in the City of Newport News, James City County, and York County. The work widened I-64 from 1.05 miles west of Route 199 (Humelsine Parkway / Marquis Center Parkway) near exit 242 to where the Segment I project ends at 0.54 miles east of Route 238 (Yorktown Road) near exit 247. This extends the three-lane section of I-64 from the point where the I-64 Segment I project ends west for approximately 7.08 miles.
“The main reason for the project is the 7-mile section of roadway, roughly from Williamsburg to Newport News area,” Ben Bushey, senior project manager for contractor Allan Myers, told Roads & Bridges. “It is a very congested area, and the widening of three lanes just alleviates a lot of the congestion. And it was done to reduce the amount of traffic that was coming through—giving them three lanes instead of two. The reason for the widening, pavement reconstruction, and new asphalt was the old pavement was not up to snuff and they needed more capacity, so they widened it.”
Aside from the additional 12-ft travel lanes and 12-ft shoulders, the improvements in Segment 2 included pavement reconstruction of the existing lanes and widening of nine existing bridges and six box culverts that lie inside the project limits.
The goal of these improvements is to increase capacity, bring portions of the interstate up to current design standards, provide more lanes for evacuation, improve safety by reducing congestion, and improve vehicular level of service, according to VDOT.