BRIDGE CONSTRUCTION: Bayonne Bridge work in New Jersey to be completed ahead of schedule
May 3, 2017
Gov. Christie says work on the bridge will be finished by the end of June, six months ahead of schedule
Work to remove the lower roadway of the Bayonne Bridge, allowing bigger cargo ships to reach New York City-area ports, will be completed six months ahead of schedule, New Jersey Gov. Chris Christie said Tuesday.
The Republican governor said the work, part of a $1.6 billion project, is expected to be done by June 30.
The Bayonne Bridge currently has a navigational clearance of 151 ft. The newly raised roadway will provide a clearance of 215 ft—the same as the nearby Verrazano-Narrows Bridge in New York.
The previous height limited the size of vessels that could pass underneath on the way to the New Jersey ports of Newark and Elizabeth. Ships' masts passed mere feet below the span. Officials say the larger ships will reduce operating costs for shipping lines. The larger ships are expected to be able to pass under later this year.
The new roadway has wider lanes and a median.
The Bayonne Bridge is the first Port Authority bridge to use cashless tolls, where drivers either use the E-ZPass electronic toll collection system or get a bill in the mail.
Extend the lifespan and durability of any concrete. PoreShield is a USDA BioPreferred product and is approved for residential, commercial, and industrial use. It works great above...
The concrete at the Indiana State Fairgrounds & Event Center is subject to several potential sources of damage including livestock biowaste, food/beverage waste, and freeze/thaw...
PoreShield is a cost-effective, nontoxic alternative to traditional concrete sealers. It works differently, absorbing deep into the concrete pores to block damage from salt ions...