Work calls for a complete reconstruction of I-4 from the Tampa interchange of I-4 and I-275, which is the major east-west connection across Central Florida. This segment also contains the highest level of aesthetic treatments for any interstate reconstruction project by the FDOT.
Location: Tampa, Fla.
Cost: $155 million
Length: 2.759 miles
Designer: Parsons Brinckerhoff
Owner: Florida DOT
Contractors: Prime—Kiewit Southern Corp.