Roads & Bridges magazine (RB)

Arlington Heights, IL 60005

COMPANY OVERVIEW

About Roads & Bridges magazine (RB)

Contact

3030 W. Salt Creek Lane
Suite 201
Arlington Heights, IL 60005
USA
https://www.cdsreportnow.com/renew/now?r
847-391-1000
847-390-0408

More Info on Roads & Bridges magazine (RB)

Products

1-Rich
Bridges

The Richmond-San Rafael Bridge

Oct. 30, 2019
The Richmond-San Rafael bridge sits in between perhaps the most dangerous and sensitive zone for an elevated structure in the world. It’s just 4 miles from the Hayward Fault and...
No
Directory

Number 1: I-355 South Extension

Dec. 5, 2006
They sat like two stags at a dance party. For well over a decade, a pair of obese and stiff bridge columns looked lonely and desperate for action as traffic did all the shakin...
No.-3-bridge1
Directory

Number 3: Rte. 9 over the Bass River

Dec. 5, 2006
To combat the salt-water environment, the bridge has several durability-increasing features. All beams are made of precast concrete, and high-performance concrete was used throughout...
No
Safety

Number 3: Gates Pass Safety Improvement Project

Dec. 5, 2006
Perhaps the most complex on the Top 10 list, the job improved a steep and narrow two-lane roadway that consisted of 9- to 10-ft-wide lanes. Two, 10-hour shifts working seven days...
No
Directory

Number 5: I-83 Relocation/Improvement, Exits 14 and 15

Dec. 5, 2006
This project sought to improve roadway conditions through the improvement of the existing roadway geometry, signalization at ramp intersections, construction of turning lanes ...
911
Directory

Number 9: J.T. Butler Blvd. Interchange and State Road 9A

Dec. 5, 2006
A 2,072-ft-long trestle bridge over wetlands and the Sawmill Slough environmental area is the centerpiece of this job. The bridge will be built on concrete girders instead of ...
No.-8-bridge1
Bridges

Number 8: Perry Street Bridge Replacement

Dec. 5, 2006
The challenge of this project was to construct a replacement bridge at the same location and with a similar appearance to the old concrete barrel arch bridge in one year without...
No.-7-bridge1
Directory

Number 7: Monroe Street Viaduct Replacement

Dec. 5, 2006
The Monroe Street bridge consists of a three-span continuous steel-girder section that crosses over the railroad/light-rail line. The location under a portion of I-95 restricted...
No.-1-bridge1
Bridges

Number 1: Benicia-Martinez Bridge

Dec. 5, 2006
“We have a number of different types of structures in the Bay Area,” David Ambuehl, construction manager for Caltrans on the Benicia-Martinez job, told ROADS & BRIDGES. “With...
No
Directory

Number 8: Larimer Square Reconstruction

Dec. 5, 2006
Speed and precision gave life to this project. Crews poured over 600 cu yd of concrete in less than 10 business days through downtown Denver. Location: Denver Cost: $570,000 Length...
1011
Bridges

Number 10: Fremont Bridge Approach Replacement

Dec. 5, 2006
The contractor had to cut a four-lane bridge down the centerline to maintain two lanes of traffic throughout the project. Efforts were made to minimize noise and vibration to ...
No.-4-bridge1
Bridges

Number 4: Hickory Street Bridge

Dec. 5, 2006
The designer included special architectural treatments in the bridge’s design, including arch-façade panels. Mussel surveys that protected habitat in the project site also were...
No
Directory

Number 6: I-85/Rte. 316 and HOV Lane Extension

Dec. 5, 2006
The most complete on the Top 10 list, this project calls for the reconstruction of 13 bridges and the addition of 17.5 miles of HOV lanes. Crews also will add 11 miles of new ...
No
Directory

Number 10: U.S. 395/Clear Acre Interchange

Dec. 5, 2006
A busy interchange in close proximity and intersecting with two major arterials, work consisted of demolishing and rebuilding two freeway bridges and one overpass at their existing...
New21
Bridges

Number 2: Lime Kiln Bridge

Dec. 5, 2006
This open-spandrel concrete arch is the only highway bridge of its kind in Vermont. The bridge has precast/prestressed concrete box beam approach spans made of high-performance...
No
Directory

Number 4: SmartFIX40/Reconstruction of I-40

Dec. 5, 2006
SmartFIX40 is TDOT’s first large accelerated project and most expensive to date. The project widens and improves safety on I-40 and rebuilds the interchange with James White Parkway...
No
Directory

Number 7: I-4 Segment 3A/3B Reconstruction

Dec. 5, 2006
Work calls for a complete reconstruction of I-4 from the Tampa interchange of I-4 and I-275, which is the major east-west connection across Central Florida. This segment also ...
211
Directory

Number 2: U.S. Rte. 15, Section D52

Dec. 5, 2006
With accidents on the rise, PennDOT decided to convert Rte. 15 from a two-lane arterial to a four-lane access highway. When completed, the corridor will be designated as I-99....
No.-6-bridge2
Bridges

Number 6: I-355 Extension Bridge

Dec. 5, 2006
This bridge will rise 90 ft above the ground at its highest point. It is the focal point of a project that will reduce congestion in one of the fastest-growing counties in the...
No
Directory

Number 9: GRIP I-40/Coors Design-Build Project

Dec. 5, 2006
As the second-busiest intersection in New Mexico, the reconstruction of the I-40/Coors Blvd. Interchange was necessary to enhance safety and improve traffic flow. Crews had to...

All content from Roads & Bridges magazine (RB)

No
Directory

Number 5: Sanibel Island Causeway Reconstruction

Dec. 5, 2006
This job requires the construction of three separate bridges to connect Sanibel with Fort Myers. Bridge A will be a 70-ft vertical clearance fixed-span bridge. Bridge B will be...
4
Bridges

I-10 Bridge Reconstruction, Pensacola, Fla.

Nov. 1, 2005
In the wake of Hurricane Ivan, crews worked around the clock to move this 7,500-ft critical transportation route back into service. The job took just three months to complete....
7
Bridges

John W. Tisdale Memorial Bridge, Clarksville, Va.

Nov. 1, 2005
The Tisdale Bridge is a critical segment of the Clarksville Bypass Project. Challenges include the complex alignment that involves tangent section transitioning to a compound ...
5
Bridges

Youghiogheny Reservoir Steel Bridge, Fayette and Somerset Counties, Pa.

Nov. 1, 2005
The as-designed 12-span concrete bridge was redesigned to an eight-span steel structure. Steel girders allowed lengthening spans, and the alternate design translated into an 11...
2
Directory

Galveston Causeway, Galveston, Texas

Nov. 1, 2005
When completed in 2008, this bridge will stand 8,592 ft long. Shallow water necessitated the construction of a temporary bridge, and hot temperatures called for nighttime work...
6
Bridges

I-580 Bridge, Reno, Nev.

Nov. 1, 2005
This 1,722-ft concrete arch bridge is being built on the side of a hill and a temporary bridge has been built to access the north side of the project. The span is located at an...
9
Bridges

Gateway Blvd. Bridge, Nashville, Tenn.

Nov. 1, 2005
This project features a number of firsts for bridges in Tennessee, including the first fixed, through-arch bridge designed and constructed in the state; the first bridge in Nashville...
3
Bridges

Doremus Avenue Bridge Replacement, Newark, N.J.

Nov. 1, 2005
This bridge, completed in December of 2003, also had a lot of action underneath. The 1,315-ft span crossed over 33 active railroad tracks, calling for tight coordinating and scheduling...
10
Bridges

Liberty Memorial Bridge, Bismarck, N.D.

Nov. 1, 2005
NDOT decided to build a new four-lane bridge to replace a span listed on the National Register of Historic Places. The existing structure must be kept open to traffic during constructio...